PROJECT:
Waikato 50 Raw Water Intake Floating Pump Station from concept to reality.
MTL ROLE:
MTL were engaged by Watercare Services Ltd, to provide the design, construction monitoring and commissioning of the raw water intake floating pumping station of the Tuakau Waikato 50 Water Treatment Plant.
This fast-track project was part of the River to Redoubt (R2R) programme of works. The raw water pump station is now fully commissioned, delivering up to 60 MLD to the WTP.
MTL delivered the design of this project within a 16-week timeframe, integrating our scope with all project stakeholders seamlessly, and adopting an agile design process.
PROJECT OUTCOME:
Fully commissioned in July 2021, relieving Auckland’s water shortages.
PROJECT PARTNERS:
Watercare Services Limited, Beca Consulting Ltd, Brian Perry Civil, JP Marshall.