PROJECT:

Connection of production well to Power Station production facilities.

MTL ROLE:

MTL were engaged as the designer to connect the new production well into existing production piping system. The detailed design included the design of the high pressure wellhead piping, two-phase cross country piping, tie-in piping and civil/structural design of all pipe supports and foundations.

The wellhead piping had the challenges of an unusually high design pressure and temperature of 112barg and 320°C. The two phase pipeline is DN500 and runs 1.1km from the production well pad to the existing two phase production line.

PROJECT OUTCOME:

The project was constructed in 2013, and started producing in 2014. MTL worked closely with the client to deliver a pipeline that suited their requirements while offering sound and efficient engineering solutions.

PROJECT PARTNERS

Transfield Worley.